We’re almost there! The building is 95% closed in and the heating systems have been started in both the south and north lean-to's and the main building floor. The overhead crane has been installed and Canadian Crane will complete the electrical installation and commissioning by mid February.

 

All of the main exhaust fans and drying units have been installed and the ducting is about 80 to 85 percent complete. Compressed air equipment is currently being installed and piping will start late February. All electrical and system controls are progressing in line with the equipment installation.

 

Just before Christmas staff moved into the office and the workers started using the lunch area.

 

Our plan at this time is to start putting the equipment through test runs the last week of February. Once that is done we will commission and start the curing equipment the first week of March. Our goal at this time is to get the building functioning with all of the heating and curing systems running for use by the middle of March.